Friday, November 20, 2026 Editions
Latest
Trending
US

Orcas Island, Washington: State of Emergency Declared as Cracks Cut Ferry Terminal Freight

San Juan County declared a state of emergency after inspectors found cracks in two steel beams under the Orcas Island ferry dock, barring trucks and cutting the island supply line.

Read inENESNEHIFR
Orcas Island, Washington: State of Emergency Declared as Cracks Cut Ferry Terminal Freight
Photo: Joe Mabel, CC BY-SA 3.0, via Wikimedia Commons (https://commons.wikimedia.org/wiki/File:Orcas_ferry_dock_01.jpg)

Key points

  • San Juan County has declared a state of emergency on Orcas Island after inspectors found cracks in the steel beams that support the ferry terminal, the one dock that carries nearly all vehicle…
  • Washington State Ferries put weight and size limits on the terminal on Monday, November 9.
  • Engineers using specialized equipment during a routine inspection found cracks in two steel support beams beneath the vehicle wheel path of the transfer span, the movable bridge deck that links a…

San Juan County has declared a state of emergency on Orcas Island after inspectors found cracks in the steel beams that support the ferry terminal, the one dock that carries nearly all vehicle traffic to and from the island.

Washington State Ferries put weight and size limits on the terminal on Monday, November 9. Only standard passenger vehicles 22 feet long or shorter and under 8,000 pounds may load and unload at the Orcas Island dock. Vehicles longer than 22 feet are barred from boarding Orcas bound ferries at Anacortes, Shaw, Lopez and Friday Harbor, and the ferry system is waiving no show fees for travelers holding reservations for oversized vehicles.

Cracks under the wheel path

Engineers using specialized equipment during a routine inspection found cracks in two steel support beams beneath the vehicle wheel path of the transfer span, the movable bridge deck that links a ferry to the dock. The limits took effect Monday to protect the structure while engineers assessed the damage.

The San Juan County Council voted on Tuesday, November 10, to declare a state of emergency. The declaration says the threat of disrupted ferry service demands immediate action to protect public health and life on Orcas Island by keeping essential services running. The county has asked the governor and state agencies for help, including financial assistance for local businesses and technical and logistical support for the repair.

Food, medicine and garbage by barge and air

The restriction blocks the trucks that carry food shipments, medical supplies, fuel and sanitation loads to the island. Providers have turned to contracted barges, which county officials say have limited space and high operating costs. The Orcas Island Market, the island largest grocery store, received a 22,000 pound shipment of groceries by barge on Wednesday night. Medication shipments are arriving by air, and UPS is delivering packages in a fleet of vans instead of its larger trucks. Residents have been asked to hold their garbage for a few extra days.

County councilmember Justin Paulsen, who lives on Orcas Island, said the community is coping. "The status on the island right now is actually pretty good," Paulsen said. "We are still able to move commuter vehicles on and off the island, which is a major plus." He said state officials responded swiftly and called the repair the transportation department top priority. Paulsen said the last comparable event came in 1999, when the ferry Elwha damaged the dock and cut Orcas Island off for three months.

Repairs could take two weeks

Contractors have installed scaffolding so crews can work beneath the transfer span. Instead of field welding, engineers plan to reinforce the span with heavy steel plates joined by high strength bolted connections, a design chosen to speed the work. Washington State Ferries estimates repairs could take up to two weeks, and engineers are studying interim safety measures that could let larger vehicles cross before the full repair is finished. The county emergency management office is monitoring supply lines with local businesses and barge operators until normal service resumes.

Timeline

  1. Nov 9, 2026Washington State Ferries bars vehicles longer than 22 feet or heavier than 8,000 pounds at the Orcas Island terminal after an inspection finds cracks in two steel support beams under the transfer span.
  2. Nov 10, 2026The San Juan County Council votes to declare a state of emergency, warning that disrupted ferry service threatens public health and essential services on Orcas Island.
  3. Nov 11, 2026A barge delivers a 22,000 pound grocery shipment to the Orcas Island Market as medication arrives by air and delivery firms switch to vans.
  4. Nov 12, 2026Washington State Ferries estimates repairs using steel reinforcement plates could take up to two weeks, while engineers study interim measures for larger vehicles.

Sources