Omaha, Nebraska: Build OMA nawikaran ke tahat Eppley Airfield 4 November ko apne pehle naye gate kholega
Dakshin terminal ke yatri budhwar, 4 November se gate A1, A1A, A1B aur A2 ka upyog karenge. Yeh lagbhag 1 arab dollar ke Build OMA terminal karyakram ka janta ke liye khulne wala pehla hissa hai. Eppley Airfield par nirman 2028 tak jari rahega.
मुख्य बिंदु
- Omaha Airport Authority ne budhwar, 28 October ko ghoshana ki ki Build OMA Terminal Modernization Program ka agla charan budhwar, 4 November ko khulega, jab Eppley Airfield ke dakshin terminal ke…
- Naye gate A1, A1A, A1B aur A2 hain.
- Nayi jagah ke andar yatriyon ko nawikaran ki gayi seating, atirikt charging station, bade shauchalaya, maaon ke kamre aur pariwarik shauchalaya milenge.
Omaha Airport Authority ne budhwar, 28 October ko ghoshana ki ki Build OMA Terminal Modernization Program ka agla charan budhwar, 4 November ko khulega, jab Eppley Airfield ke dakshin terminal ke yatri naye concourse ke ek hisse ka upyog shuru karenge. Yeh lagbhag 1 arab dollar ke karyakram ka yatri janta ke liye khulne wala pehla hissa hai.
Naye gate A1, A1A, A1B aur A2 hain. Shuruaat mein dakshin terminal se chalne wali airlines inka upyog karengi. Yatri aaj ki tarah hi suraksha janch se guzrenge aur naye gate ki ore ishara karne wale sanketon ka palan karenge, authority ne kaha.
Nayi jagah ke andar yatriyon ko nawikaran ki gayi seating, atirikt charging station, bade shauchalaya, maaon ke kamre aur pariwarik shauchalaya milenge. November mein dakshin terminal ke yatriyon ke liye kai naye airport storen mein se pehle store bhi khulenge.
"Yeh OMA ke liye aur naye terminal ko jeevan dene ke liye kaam karne wale hazaron logon ke liye ek romanchak pal hai," Omaha Airport Authority ke mukhya karyakari adhikari Dave Roth ne kaha. Roth ne kaha ki yatri pehli baar kuch nayi jagahon aur suvidhaon ko dekh payenge, jabki abhi bahut kaam baki hai.
Aage kya khulega
2027 ki shuruaat mein central pavilion aur unified concourse ke aur hisse khulenge, aur sabhi yatri naye terminal anubhav mein aa jayenge. Us samay aur store khulenge, saath mein ek airport lounge aur ek kendrikrit suraksha janch chauki bhi khulegi.
Authority karyakram ke bache charanon ko pura karti rahegi aur nirman 2028 tak jari rahega, jismein antarrashtriya udaanon ki kshamata bhi shamil hai. Nirman ke dauran yatriyon ko lena aur chhodna dakshin garage ke level 1 par hi rahega, jabki dal terminal ke saamne ke hisson ka nawikaran karenge. 2028 mein pariyojana poori hone par lena aur chhodna terminal ke saamne wale drive par laut jayega.
KETV ne is saptah yatriyon ko nawikaran kiye gaye gate kshetra ki pehli jhalak dikhai, aur bataya ki yatriyon ko abhi saalon tak nirman badlavon ka saamna karna padega. WOWT ne September mein bataya tha ki nirman 60 pratishat pura ho gaya hai. Authority ke mukhya rananiti adhikari Steve McCoy ne WOWT ko bataya tha ki airport mool February yojana se pehle wartaman dakshin concourse se jude chaar naye gate kholega, jinmein kahin bade pratiksha kaksh, naye finish, bade shauchalaya aur anya takneeki sudhar honge.
Punahnirman ke beech ek wyast kshetriya airport
Eppley Airfield Nebraska aur Iowa kshetra ka sabse bada airport hai. Isne 2025 mein 5.2 million se adhik yatriyon ki sewa ki. Authority ke anusar saat airlines Omaha se 37 nonstop gantabyon ke liye rozana lagbhag 75 prasthan deti hain.
Roth ne kaam jari rehne tak yatriyon se dhairya rakhne ka agrah kiya. "Hum jante hain ki yatri OMA mein ho rahi pragati dekhne ke liye utsuk hain, aur yeh gate purvavalokan unhein ise pehli baar khud dekhne ka mauka deta hai," unhone kaha. Yatri BuildOMA.com par pariyojana ko dekh sakte hain aur yatra jankari prapt kar sakte hain.
Srot
Grow Omaha dwara 28 October 2026 ko prakashit Omaha Airport Authority ki ghoshana. EIN Nebraska newswire par 28 October 2026 ko aayi, nawikaran kiye gaye gate kshetra ki pehli jhalak par KETV ki report. 4 September 2026 ki, Build OMA nirman 60 pratishat tak pahunchne par WOWT ki report.
टाइमलाइन
- Sep 4, 2026WOWT batata hai ki Eppley Airfield par Build OMA nirman 60 pratishat pura ho gaya hai, aur wartaman dakshin concourse se jude chaar naye gate mool February yojana se pehle khulenge.
- Oct 28, 2026Omaha Airport Authority ghoshana karti hai ki pehle naye gate 4 November ko khulenge. KETV yatriyon ko nawikaran kiye gaye gate kshetra ki pehli jhalak dikhata hai.
- Nov 4, 2026Dakshin terminal ke yatri naye concourse mein gate A1, A1A, A1B aur A2 ka upyog shuru karte hain, aur November mein pehle naye store khulte hain.
- Early 2027Central pavilion aur unified concourse ke aur hisse khulte hain, jinmein atirikt store, ek airport lounge aur ek kendrikrit suraksha janch chauki shamil hai.
- Late 2028Nirman samapt hota hai, jismein antarrashtriya udaan kshamata shamil hai, aur yatriyon ko lena aur chhodna terminal ke saamne wale drive par laut jata hai.