Detroit, Michigan: $2.2 Billion RenCen Plan Moves to Full Council Without a Recommendation

A council committee split on Thursday after a meeting that ran from 10 a.m. to nearly 5:30 p.m. and sent the Bedrock and General Motors riverfront package onward without a recommendation.

Read inENESNEHIFR
Detroit, Michigan: $2.2 Billion RenCen Plan Moves to Full Council Without a Recommendation
Photo: Michael Barera, CC BY-SA 4.0, via Wikimedia Commons (https://commons.wikimedia.org/wiki/File:Detroit_May_2023_08_(Renaissance_Center_from_William_G._Milliken_State_Park_and_Harbor).jpg)

Key points

  • The $2.2 billion plan to remake Detroit's Renaissance Center cleared a long and divided committee meeting on Thursday and now goes to the full City Council, which could vote as soon as Tuesday,…
  • The meeting began at 10 a.m. at the Coleman A.
  • Chair Latisha Johnson and Coleman Young II voted to send the plan to the full council.

The $2.2 billion plan to remake Detroit's Renaissance Center cleared a long and divided committee meeting on Thursday and now goes to the full City Council, which could vote as soon as Tuesday, Nov. 17. Members of the council's Planning and Economic Development Committee voted to move the Bedrock and General Motors package of tax breaks, incentives and community benefits forward without a recommendation.

The meeting began at 10 a.m. at the Coleman A. Young Municipal Center and did not end until shortly before 5:30 p.m. The hearing room was at first too small for every member of the public who wanted to attend in person, and residents also joined online. The committee heard several rounds of public comment, and residents asked the council to slow the process down.

A split committee

Chair Latisha Johnson and Coleman Young II voted to send the plan to the full council. Gabriela Santiago-Romero voted no. Johnson said she still has questions about the project's nonprofit ownership model and would like to see changes to the proposed incentives, but she said the full council should now question the developers directly. Santiago-Romero said the approval process has been rushed. She said she wants to make sure the city is not building for the weekend or for downtown only, and that people move to cities for their transportation, their neighborhoods, their culture and their people.

Before the committee acted, a nine-member Neighborhood Advisory Council of resident volunteers voted 8 to 1 on Oct. 27 to recommend the community benefits package. Teron Haynes Jr. cast the only no vote, citing the lack of direct public ownership and revenue sharing with the city.

What the plan would build

The redevelopment would run in phases over a decade in two parts. The first is a $1.6 billion rebuild of the original Renaissance Center towers, including the demolition of two of the five towers. The second is a $624 million buildout of the 30-acre east riverfront next to the RenCen as public space. The project is seeking $548 million in incentives and carries a $133 million community benefits package of commitments and gifts. A new nonprofit organization would develop, own and operate the project. Dan Gilbert is personally contributing $1 billion in equity, and GM is putting in $250 million.

Why the developers want a fast vote

Bedrock and GM want all local approvals in hand before the council's December recess. The developers cite a concern that incoming Gov. Jocelyn Benson could change the approval process for large development incentives when she takes office in 2027, which could add long delays. If the full council approves the package, a final vote on state incentives would still come later from the Michigan Strategic Fund in Lansing. Developers have said they want to start work next summer.

Timeline

  1. Oct 27, 2026The nine-member Neighborhood Advisory Council votes 8 to 1 to recommend the community benefits package for the RenCen redevelopment. Teron Haynes Jr. is the only no vote.
  2. Nov 12, 2026The City Council Planning and Economic Development Committee meets from 10 a.m. to shortly before 5:30 p.m. and sends the $2.2 billion package to the full council without a recommendation.
  3. Nov 17, 2026The full City Council could vote as soon as Tuesday, Nov. 17, keeping the plan on pace for a decision before Thanksgiving.