The Oregonian reports the Trail Blazers have not answered a city term sheet or supplied renderings and a budget for the $600 million Moda Center renovation, so a December deadline for $365 million in state money will almost certainly be missed.

Read inENESNEHIFR
Portland, Oregon: Moda Center Renovation Deal Likely to Miss December Deadline, State Funding at Risk

Key points

  • Portland leaders and the Trail Blazers will almost certainly miss a December deadline to finalize a deal for a $600 million renovation of the Moda Center, according to a report by Shane Dixon…
  • Multiple sources told The Oregonian that Blazers officials have not formally responded to a term sheet the Portland City Council approved this summer.
  • Without those pieces, city lawmakers will not approve a final agreement before the December deadline the state set to unlock its $365 million, the sources said.

Portland leaders and the Trail Blazers will almost certainly miss a December deadline to finalize a deal for a $600 million renovation of the Moda Center, according to a report by Shane Dixon Kavanaugh and Bill Oram of The Oregonian. Missing the deadline would put the state's planned $365 million contribution at risk, along with $120 million pledged by the city and $88 million from Multnomah County.

What has not arrived

Multiple sources told The Oregonian that Blazers officials have not formally responded to a term sheet the Portland City Council approved this summer. The team has also not provided the community benefit and project labor agreements the governments asked for, and it has not produced architectural renderings or a budget for the proposed makeover, despite requests from the state, the city and the county.

Without those pieces, city lawmakers will not approve a final agreement before the December deadline the state set to unlock its $365 million, the sources said. Portland City Council President Jamie Dunphy told The Oregonian: "That timeline is simply not going to happen at this point. There's not been meaningful progress. We've not got into any brass tacks about what we're buying with $600 million."

The points of dispute

The two sides remain divided over a provision that would require the team to maintain the Moda Center in first-class condition. Controlling owner Tom Dundon has also not committed to a 20-year extension of the lease, which state lawmakers required as a condition of the state funding, according to the sources cited by The Oregonian.

Multnomah County Commissioner and Chair-elect Shannon Singleton told The Oregonian the county stopped holding weekly meetings on the project in October and has had no recent updates. "I don't feel super hopeful at this time," she said of reaching a final agreement by the deadline.

Oregon officials need a final lease agreement ready by next month so the state can begin selling bonds to finance its share. Betsy Imholt, director of the state Department of Administrative Services, wrote to the city council in July that selling bonds is an expensive and time-consuming process the state will not start unless it is certain all conditions have been met.

The team response and what happens next

The Blazers issued a statement on Thursday. Team spokesperson Charles Boyle said: "The Trail Blazers are essential to Portland's identity, and securing long-term success for the team and the city-owned arena is critically important to our state. We remain fully committed to working with our public partners to finalize an agreement."

Missing the deadline would be a major setback, but it would not by itself end the renovation effort or the team's stay in Portland. The Blazers' current lease on the Moda Center runs through 2030, which leaves time to return to negotiations. What is not clear, The Oregonian reported, is whether the state would still offer the same contribution later, or whether a renovation of this size is possible without that money in place.

Portland officials have said an agreement needs to be in place by late November so the council can vote on a final proposal before its mid-December recess.

Timeline

  1. Summer 2026The Portland City Council approves a term sheet for a Moda Center renovation deal. The Oregonian reports the Blazers have not formally responded to it.
  2. Oct 2026Multnomah County stops holding weekly meetings on the project, Commissioner and Chair-elect Shannon Singleton tells The Oregonian, with no recent updates since.
  3. Nov 13, 2026The Oregonian reports that Portland leaders and the Trail Blazers will almost certainly miss the December deadline to secure public funding for the $600 million renovation, putting the state's $365 million contribution at risk.
  4. Dec 2026The state deadline to unlock its $365 million contribution falls in December. Portland officials have said a deal needs to be in place by late November for a council vote before the mid-December recess.

Sources